Comprehensive Plan: The village has not begun planning or scheduling for the completion of the Comprehensive Plan for future growth.
Basic process of approval or denial of a development plan:
• 1st Meet with Staff
• 2nd Proposal goes to Village Board
• 3rd Village Board makes referral to Plan Commission
• 4th Plan Commission does its work & makes recommendation to village board
5th Village Board has the final word
Projects also need to go to the Building Board for approval
TIF Districts: The village has not implemented any TIF Districts in the past.
Redevelopment Aid: The village does not offer any special programs for redevelopment.
Fee Schedule:
1) Conditional Use $300
2) Any other permit or fee required min. $50
Time Schedule for Plan Approval: The average amount of time from submittal to final approval for a new development is about 3 to 6 months for large projects and 6 to 8 weeks for smaller projects.
Building or Growth Moratoria: There are no building or growth moratoria in place now.
Environmental Issues: None specifically listed.
Single Development Department: There is not a single department that handles it all. It is a joint effort involving the Building Inspector, Engineer, Police, North Shore Fire Dept. and Village Administration.
Internet Connection: www.vil.fox-point.wi.us
– A variety of downloadable licenses, permits, and fees
– Meeting Schedules for different commissions/committees including agendas and minutes
– The most common and frequently requested ordinances
– “Construction Project Update” Link
– Contact Information