Crews for J.H. Findorff & Son Inc. recently completed a 19-hour mat pour of 3,750 cubic yards of concrete for the foundation of The Moderne, a 30-story residential building under construction at the southwest corner of Old World Third Street and Juneau Avenue in downtown Milwaukee.

The concrete was poured into a 7-foot thick mat slab. The concrete equates to about 7,700 tons or more than 15 million pounds of material.

It took 380 truck loads of concrete to complete the mat pour. Each truck took about three minutes to unload its concrete during the 19-hour pour.

“The success of (the mat pour) was the result of a well-planned and well executed collaborative effort on all fronts,” said Eric Wynn, general manager of Findorff. “There was an overwhelming surge of positive energy during the entire 19-hour pour. Everyone had a great sense of pride for the work that was taking place and the effect this work would have on the city. It was a great thing to be a part of.”

Once it is completed in 2012, The Moderne will be the tallest building west of the Milwaukee River in downtown Milwaukee. It will have 203 apartments, 14 condominiums and first floor retail space.

Get the BizTimes email newsletter
Keep up with the issues, companies and people that matter most to business in the Milwaukee metro area.
Andrew is the editor of BizTimes Milwaukee. He joined BizTimes in 2003, serving as managing editor and real estate reporter for 11 years before being promoted to editor in 2015. An award-winning journalist, Weiland is a five-time winner in the Milwaukee Press Club Excellence in Journalism Awards contest and a five-time winner in the Alliance of Area Business Publishers (AABP) Awards contest. BizTimes Milwaukee has won 45 AABP awards for design and journalism during his time as editor. He is also a regular guest on WISN-TV Channel 12's 4 p.m. newscast to discuss the week's most significant business news stories.

Crews for J.H. Findorff & Son Inc. recently completed a 19-hour mat pour of 3,750 cubic yards of concrete for the foundation of The Moderne, a 30-story residential building under construction at the southwest corner of Old World Third Street and Juneau Avenue in downtown Milwaukee.


The concrete was poured into a 7-foot thick mat slab. The concrete equates to about 7,700 tons or more than 15 million pounds of material.

It took 380 truck loads of concrete to complete the mat pour. Each truck took about three minutes to unload its concrete during the 19-hour pour.

"The success of (the mat pour) was the result of a well-planned and well executed collaborative effort on all fronts," said Eric Wynn, general manager of Findorff. "There was an overwhelming surge of positive energy during the entire 19-hour pour. Everyone had a great sense of pride for the work that was taking place and the effect this work would have on the city. It was a great thing to be a part of."

Once it is completed in 2012, The Moderne will be the tallest building west of the Milwaukee River in downtown Milwaukee. It will have 203 apartments, 14 condominiums and first floor retail space.

Holiday flash sale!

Limited time offer. New subscribers only.

Subscribe to BizTimes Milwaukee and save 40%

Holiday flash sale! Subscribe to BizTimes and save 40%!

Limited time offer. New subscribers only.

Exit mobile version