Foxconn starts concrete foundation pour in Mount Pleasant

Crews begin pouring foundations at the Foxconn campus in Mount Pleasant on June 19.

Construction crews have started pouring more than 65,000 cubic yards of concrete to form the footings and foundations for Foxconn Technology Group’s first manufacturing facility at its planned Mount Pleasant campus.

Foxconn in late May awarded $13 million in contracts for foundation related work for its 988,999-square-foot facility. Excavation and concrete foundation work went to Fond du Lac-based C.D. Smith Construction Inc.

“Today marks another milestone for Foxconn in Wisconsin,” said Louis Woo, special assistant to Foxconn founder Terry Gou. “The installation of foundations and footings comes after months of careful planning and preparation, which demonstrates Foxconn’s concrete commitment to advanced manufacturing in Wisconsin.”

Foxconn originally announced plans for a Gen 10.5 LCD manufacturing facility aimed at making the largest displays in the world. The company has since shifted to a Gen 6 facility to allow for additional product flexibility.

Woo said the company was proud of the progress made over the last year and would be continuing to work toward beginning production at its facility in the fourth quarter of 2020.

Arthur covers banking and finance and the economy at BizTimes while also leading special projects as an associate editor. He also spent five years covering manufacturing at BizTimes. He previously was managing editor at The Waukesha Freeman. He is a graduate of Carroll University and did graduate coursework at Marquette. A native of southeastern Wisconsin, he is also a nationally certified gymnastics judge and enjoys golf on the weekends.
Construction crews have started pouring more than 65,000 cubic yards of concrete to form the footings and foundations for Foxconn Technology Group’s first manufacturing facility at its planned Mount Pleasant campus. Foxconn in late May awarded $13 million in contracts for foundation related work for its 988,999-square-foot facility. Excavation and concrete foundation work went to Fond du Lac-based C.D. Smith Construction Inc. “Today marks another milestone for Foxconn in Wisconsin,” said Louis Woo, special assistant to Foxconn founder Terry Gou. “The installation of foundations and footings comes after months of careful planning and preparation, which demonstrates Foxconn’s concrete commitment to advanced manufacturing in Wisconsin.” Foxconn originally announced plans for a Gen 10.5 LCD manufacturing facility aimed at making the largest displays in the world. The company has since shifted to a Gen 6 facility to allow for additional product flexibility. Woo said the company was proud of the progress made over the last year and would be continuing to work toward beginning production at its facility in the fourth quarter of 2020.

BIZEXPO IS MAY 13 -  Early Registration Ends May 1

Stay up-to-date with our free email newsletter

Keep up with the issues, companies and people that matter most to business in the Milwaukee metro area.

By subscribing you agree to our privacy policy.

No, thank you.

Holiday flash sale!

Limited time offer. New subscribers only.

Subscribe to BizTimes Milwaukee and save 40%

Holiday flash sale! Subscribe to BizTimes and save 40%!

Limited time offer. New subscribers only.

Exit mobile version